Framing the Golf Course Restrooms

Over the Memorial Say weekend I gathered some volunteers to help me frame the new Restrooms for the Hide-A-Way Hills Golf Course.



The 3 day weekend was hot, but luckily the rain stayed away so we could get the framing portion done.


Now that the building is framed we can shingle the roof, install the doors and windows, and apply the trim.


Framing Begins on Kusa Room Addition

The framing begins at our Kusa Room Addition. 2x10 floor joists are installed 16" on center to support the 3/4 " Advantech flooring panels. Advantech sub floors are both stronger and more weather resistant than either plywood or osb floors, and offer a 50 year warranty.

The floor panels are glued and nailed to the joists to avoid floor squeaks.

The walls on this project are built with 2x4 studs and 7/16 osb sheathing, which is typical for residential construction.






Back Deck

Today we began the framing on the Back Deck. The deck will be 12' x 42' with 12' x 22' under roof and screened.